Earned Value Analysis

Monitor project performance using CPI, SPI and other key metrics

Budget at Completion

$4,200,000

Total Project Budget
Planned Value

$2,856,000

68% of budget
Earned Value

$2,772,000

66% of budget
Actual Cost

$2,940,000

70% of budget

Cost Performance Index (CPI)

0.94
Under Budget
EV / AC
$2.77M / $2.94M
0.0 0.5 1.0 1.5 2.0

Schedule Performance Index (SPI)

0.97
Behind Schedule
EV / PV
$2.77M / $2.86M
0.0 0.5 1.0 1.5 2.0

Variance Analysis

Cost Variance (CV) -$168,000
Schedule Variance (SV) -$84,000

Earned Value Curve

Performance Indices

Last updated: 15 min ago

Detailed Earned Value Data

Area/Zone Budget (BAC) Planned Value (PV) Earned Value (EV) Actual Cost (AC) CPI SPI Status
Zone 1 $840,000 $588,000 $546,000 $588,000 0.93 0.93 Behind
Zone 2 $1,050,000 $735,000 $714,000 $756,000 0.94 0.97 Behind
Zone 3 $1,260,000 $882,000 $882,000 $882,000 1.00 1.00 On Track
Zone 4 $1,050,000 $651,000 $630,000 $756,000 0.83 0.97 Over Budget